HIGH Court judge, Justice Joseph Mafusire has struck off the roll an application by property developer George Katsimberis who was seeking to block cancellation of a joint venture agreement between himself and former partner, Ken Sharpe.
Sharpe withdrew from the deal after Katsimberis reneged on their agreement and failed to deliver within the agreed timeframe, leading to the litigation.
Katsimberis took Sharpe to court in 2020 for breach of contract and wanted the termination declared a nullity.
The matter was, however, removed from the roll by consent from both parties.
“Whereupon after reading documents filed of record and hearing counsel, it is ordered that by consent matter is removed from the roll pending the resolution of the application for recusal to be launched by the plaintiffs. There shall be no order as to costs,” reads the brief order by the judge.
Katsimberis and his company Halinka Investments were the plaintiffs in the matter.
Keep Reading
- Van Blerk trial deferred to July 19
- State witness exposed for fraudulently approving Katsimberis building plan
- Van Blerk trial deferred to July 19
- State witness exposed for fraudulently approving Katsimberis building plan
Sharpe had been cited in his capacity as the trustee of Kilimanjaro, Porcupine and Hamster Trusts also cited as respondents in the application.
Castlehorpe Investments Pvt Ltd and Gunhill Ecofriendly Estate Pvt Ltd were also cited as respondents.
In cancelling the agreement, Sharpe was accusing Katsimberis of failing to procure town planning approval which was to be obtained by November 2017.
He also noted that there was no development on the property.
Sharpe also said Katsimberis had failed to comply with the project's building obligations.
“We are instructed that contrary to the agreed terms of the Joint Venture agreement, Halinka has breached the terms of the Joint Venture agreement by failing to perform in accordance with its building obligations, in particular to date there has been no procurement of the town planning approval which was to be obtained by the 15th of November 2017,” wrote Sharpe's attorneys, Dube, Manikai and Hwacha.
“The town planning approval was a sine qua non to the commencement of construction of the flats on the property which was agreed to commence on the 1st of December 2017.
“To date there has been no development on the property despite our client's compliance with the terms of the joint venture agreement and several requests for Halinka to perform , in light of its failure to take timely steps to comply with its building obligations.
“Halinka’s failure to perform in accordance with its obligations as set out in the Joint venture agreement, is an unequivocal manifestation of its intention to not be bound by the terms of the Joint Venture Agreement and therefore amounts to repudation,” read the letter written to Katsimberis.
According to court papers, Katsimberis and Sharpe entered into a joint venture agreement on June 7, 2016. The parties agreed to develop some land in Harare measuring 7.663 hectares. They intended to build 600 flats on the property.
Katsimberis was to conduct a legal accounting and technical due diligence which would be carried out by Virgin Management and Chinawa Law Chambers.
After that he was to pay US$150 000 in favour of Sharpe or his nominee.
He was supposed to pay US$600 000 to enable release of the title deed to facilitate transfer of the property from Homeday Properties Pvt Ltd to the joint venture company Gunhill which was to be incorporated.
The parties were entitled to hold 50% shareholding each in the partnership.
Katsimberis was to pay US$750 000 which was to buy the stand for the flats.
Parties also agreed that upon the sale of the flats belonging the joint venture project they would share profits on an equal basis.
Katsimberis, however, allegedly delayed resulting in the cancellation of the deal.